Question: 4 0 . The critical path for the network activities shown below is with duration . Activity Duration Immediate Predecessors A 4 - - -

40. The critical path for the network activities shown below is with duration .
Activity Duration Immediate
Predecessors
A 4---
B 2 A
C 7--
D 4 A
E 5 B,C,D
a. A-B-D; 10
b. A-B-E; 11
c. C-E; 12
d. A-D-E; 13
e. A-B-C-D-E; 22
d (Project management techniques: PERT and CPM, difficult){AACSB: Analytic Skills}