Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 2 A C

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A

4

---

B

2

A

C

7

--

D

4

A

E

5

B,C,D

a. A-B-E; 11

b. C-E; 12

c. A-D-E; 13

d. A-B-C-D-E; 22

e. A-B-D; 10