Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 2 A C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | --- |
| B | 2 | A |
| C | 7 | -- |
| D | 4 | A |
| E | 5 | B,C,D |
a. A-B-E; 11
b. C-E; 12
c. A-D-E; 13
d. A-B-C-D-E; 22
e. A-B-D; 10
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
