Question: QUESTION 17 Activity Duration Immediate Predecessors A 4 - B 2 A C 7 - D 4 A E 5 B, C, D Based on

QUESTION 17

  1. Activity

    Duration

    Immediate Predecessors

    A

    4

    -

    B

    2

    A

    C

    7

    -

    D

    4

    A

    E

    5

    B, C, D

    Based on the information given from the table above. The critical path for the network activities shown above is ____ with duration _______.

    A.

    A-B-D; 10

    B.

    C-E; 12

    C.

    A-D-E; 13

    D.

    A-B-E; 11

    E.

    A-B-C-D-E; 22