Question: QUESTION 17 Activity Duration Immediate Predecessors A 4 - B 2 A C 7 - D 4 A E 5 B, C, D Based on
QUESTION 17
-
Activity
Duration
Immediate Predecessors
A
4
-
B
2
A
C
7
-
D
4
A
E
5
B, C, D
Based on the information given from the table above. The critical path for the network activities shown above is ____ with duration _______.
A. A-B-D; 10
B. C-E; 12
C. A-D-E; 13
D. A-B-E; 11
E. A-B-C-D-E; 22