Question: Assignment 1. Draw the AON diagram 2. Compute ES, EF, LS, LF, and slack time for each activity 3. How long will the project take?

Assignment 1. Draw the AON diagram 2. Compute ES, EF, LS, LF, and slack time for each activity 3. How long will the project take? What is the critical path? Immediate Activity Predecessors A B C D E F G H 1 A A B B D, E C, E F, G H Time 5 18 13 3 10 4 11 9 2