Question: ASSIGNMENT Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for

ASSIGNMENT

  • Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish.
  • Develop the Gantt chart schedule for the project to determine its estimated completion date. (Note: the template provided already has weekends and holidays removed and will start on January 3, 2017.)
  • Answer the following questions:
    • Will the project as planned meet the October 25, 2017 deadline?
    • What activities lie on the critical path?
    • How sensitive is this network?

NIGHTINGALE PROJECT

You are the assistant project manager to Rassy Brown, who is in charge of the Nightingale project. Nightingale was the code name given to the development of a handheld electronic medical reference guide. Nightingale would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations.

Rassy and her project team were developing a project plan aimed at producing 30 working models in time for MedCON, the biggest medical equipment trade show each year. Meeting the MedCON October 25, 2017 deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders for new products at MedCON. Rassy had also heard rumors that competitors were considering developing a similar product, and she knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the MedCON deadline.

The project team spent the morning working on the schedule for Nightingale. They started with the WBS and developed the information for a network, adding activities when needed. Then the team added the time estimates they had collected for each activity. Following is the preliminary information for activities with duration time and predecessors.

ActivityDescriptionDurationPredecessor
?1Architectural decisions10None
?2Internal specifications201
?3External specifications181
?4Feature specifications151
?5Voice recognition152, 3
?6Case?42, 3
?7Screen?22, 3
?8Speaker output jacks?22, 3
?9Tape mechanism?22, 3
10Database404
11Microphone/soundcard?54
12Pager?44
13Barcode reader?34
14Alarm clock?44
15Computer I/O?54
16Review design105, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15
17Price components?55, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15
18Integration1516, 17
19Document design3516
20Procure prototype components2018
21Assemble prototypes1020
22Lab test prototypes2021
23Field test prototypes2019, 22
24Adjust design2023
25Order stock parts1524
26Order custom parts?224
27Assemble first production unit1025 - Finish to start delay of 8 non-worked business days, 26
28Test unit1027
29Produce 30 units1528
30Train sales representatives1029

1. Need a Project Network Diagram

ASSIGNMENTConstruct a project network diagram for the stadium project, displaying activity ID,duration, earliest start, earliest finish, latest start, latest finish, and slack foreach activity. Assume that the final activity in the diagram will have

A B C D E F G H K LMNO P Q R S T U V W X Y Z AA AB AC AD AE AF AG AH AI AJ AK AL AM 1 PMT472L 3.2 CASE STUDY: NIGHTINGALE PROJECT - PART A Original Project Network Diagram Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram 4 finish. NOTE: Copy-paste and fill in the 3x3 cell set to create building blocks for your project network diagram. 8 ES ID EF 0 1 10 9 SL SL ? 10 LS DUR LF ? 10 ? 11 12 13 14 15 16 24 27G C O P Q S T U V A B C D E F K L M N PMT472L 3.2 CASE STUDY: NIGHTINGALE PROJECT - PART A 2 Original Gantt Chart Schedule 3 Develop the Gantt chart schedule for the project to determine its estimated completion date. 1/24/2017 1/25/2017 1/23/2017 1/18/2017 1/20/2017 1/19/2017 1/17/2017 1/13/2017 1/16/2017 1/11/2017 1/12/2017 1/5/2017 1/9/2017 1/10/2017 1/6/2017 1/3/2017 1/4/2017 4 Wed Mon Tue E E Thu Mon Tue Wed Thu Tue Wed E Mon Thu Tue Wed 5 Activity Duration (days) Start Date Finish Date Predecessor(s) 6 1 - Architectural decisions 10 1/3/2017 1/16/2017 None 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 w 4U'I 1O 11 12 13 14 15 16 17 18 19 20 91 A B C D E F G H | J K L M N PMT472L 3.2 CASE STUDY: NIGHTINGALE PROJECT - PART A Will the project as planned meet the October 25, 2017 deadline? (Enter response) What activities lie on the critical path? (Enter response) How sensitive is this network? (Enter response)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!