Question: Assignment: Earned Value Management Objective: Use earned value management ( EVM ) to assess project performance by calculating cost and schedule variances, and to forecast
Assignment: Earned Value Management
Objective: Use earned value management EVM to assess project performance by calculating cost and schedule variances, and to forecast an estimate at completion EAC
Assignment:
Following the example in the workbook and the lecture videos, use the Earned ValueManagement Template to complete the following:
You have a project which will stack blocks in days at a rate of $ per block.
At the end of day you have spent $ and have stacked blocks.
o Determine AC EV PV
o Calculate CV and CPI
o Calculate SV & SPI
o Determine BAC
o Calculate EAC
At current CPI
Earned Value Management Template
BAC
Budget at Completion
How much is the total budgeted cost for the project total
number of blocks times the budgeted cost per block
EAC at current I
Estimate at Completion
BACI
How much is the total estimated cost for the project
assuming the current cost per bock continues?
EAC For remaining work at budgeted rate
Remaining work
How much is the total estimated cost for the project if the
remaining work is back on budget?For remaining work at budgeted rate
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
