Question: Assignment: Earned Value Management Objective: Use earned value management ( EVM ) to assess project performance by calculating cost and schedule variances, and to forecast

Assignment: Earned Value Management
Objective: Use earned value management (EVM) to assess project performance by calculating cost and schedule variances, and to forecast an estimate at completion (EAC).
Assignment:
1. Following the example in the workbook and the lecture videos, use the Earned ValueManagement Template to complete the following:
You have a project which will stack 10 blocks in 10 days at a rate of $10 per block.
At the end of day 5, you have spent $50 and have stacked 4 blocks.
o Determine AC, EV, PV
o Calculate CV and CPI
o Calculate SV & SPI
o Determine BAC
o Calculate EAC
At current CPI
Earned Value Management Template
BAC=
Budget at Completion
How much is the total budgeted cost for the project (total
number of blocks times the budgeted cost per block)?
5.1
EAC at current CPI =
Estimate at Completion
BACCPI
How much is the total estimated cost for the project
assuming the current cost per bock continues?
5.2.
EAC For remaining work at budgeted rate
AC+(Remaining work xBC)
How much is the total estimated cost for the project if the
remaining work is back on budget?For remaining work at budgeted rate
 Assignment: Earned Value Management Objective: Use earned value management (EVM) to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!