Question: Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total/Free Float for the activities. Also draw the
Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total/Free Float for the activities. Also draw the Network Diagram for the given schedule, If Variance along the critical path = 16 Calculate the DEADLINE for finishing the project with a 97.5% likelihood
| Activity Name | Predecessor | Duration | ES | EF | LS | LF | TF |
FF |
| Start | - | - | 0 | 0 | 0 | 0 | - |
- |
| A | Start | 5 |
|
|
|
|
|
|
| B | A | 5 |
|
|
|
|
|
|
| C | A | 5 |
|
|
|
|
|
|
| D | B | 3 |
|
|
|
|
|
|
| E | B | 4 |
|
|
|
|
|
|
| F | C, D | 5 |
|
|
|
|
|
|
| G | D, E | 3 |
|
|
|
|
|
|
| H | F | 5 |
|
|
|
|
|
|
| I | G,H | 5 |
|
|
|
|
|
|
| End | I | - |
|
|
|
|
|
|