Question: Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total/Free Float for the activities. Also draw the

Consider the information given below and compute the Early Start, Early Finish, Late Start, Late Finish and Total/Free Float for the activities. Also draw the Network Diagram for the given schedule, If Variance along the critical path = 16 Calculate the DEADLINE for finishing the project with a 97.5% likelihood

Activity Name

Predecessor

Duration

ES

EF

LS

LF

TF

FF

Start

-

-

0

0

0

0

-

-

A

Start

5

B

A

5

C

A

5

D

B

3

E

B

4

F

C, D

5

G

D, E

3

H

F

5

I

G,H

5

End

I

-

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!