Consider the following project network. The crashing data for this project are as follows: Assume that the
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following project network.
The crashing data for this project are as follows:
Assume that the management desires a deadline of 17 weeks for project completion time.
a. What activities should be crashed, by how many weeks each and at what total cost each?
b. What is the total crashing cost?
c. Develop a linear programming model that can be used to determine the best project crashing schedule (do not solve).