assume that there is new one-day lag Finish-to-Start between activities D and E (FS = 1 day).
Fantastic news! We've Found the answer you've been seeking!
Question:
assume that there is new one-day lag Finish-to-Start between activities D and E (FS = 1 day).
- What is the normal duration and the cost of the project? Round up all costs to zero decimals.
- Which activities should you crash to meet a project deadline of 16 days? Consider that there Indirect costs are $1,500 (in normal duration of the project), and there is $100 in indirect cost savings per day saved. Draw a new AON each time you make a one-day reduction decision. Make sure you show the last AON network reaching EF = 16 days.
- What is the cost of crashing the activities you selected (no decimals)?
- What is the new TOTAL cost of the project -no decimals (i.e., crashing included to reach 16 days)?
Activity | Predecessor | Crash time (days) | Crashed cost
| Normal time (days) | Normal cost |
A | - | 3 | 5,700 | 4 | 4,100 |
B | A | 6 | 3,700 | 9 | 2,000 |
C | B | 1 | 3,500 | 4 | 2,500 |
D | A | 6 | 4,900 | 7 | 4,300 |
E | D | 3 | 2,000 | 4 | 1,600 |
F | D | 3 | 3,500 | 5 | 2,500 |
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date: