Question: Draw the project network using the AON approach. Use a START and/or END nodes as needed. Using the normal times and normal costs: Calculate the

  1. Draw the project network using the AON approach. Use a START and/or END nodes as needed.
  2. Using the normal times and normal costs:
  • Calculate the ES, EF, LS and LF of each activity.
  • Calculate and show in the nodes of your AON project network the total slack of the non-critical activities.
  • What is the normal (duration) time of the project? 
  • What are the critical activities and the critical path? 
ActivityPredecessor

Normal time

(days)

A-4
BA9
CB4
DA7
ED4
FD5