Question: Assume the network and data in the following Table A: table [ [ ACTIVITY , table [ [ Immediate ] , [ Predecessor

Assume the network and data in the following Table A:
\table[[ACTIVITY,\table[[Immediate],[Predecessor (s)]],Time (weeks)],[A,--,3],[B,--,4],[C,B,4],[D,A,4],[E,A, B,5],[F,D, E,6],[G,C, E,2]]
The duration for the project is weeks (enter response as integer).