Question: b. The duration for path B-C-G is _________ weeks (enter response as integer). c. The slack for activity C is ________ week(s) (enter response as

b. The duration for path B-C-G is _________ weeks

b. The duration for path B-C-G is _________ weeks (enter response as integer).

c. The slack for activity C is ________ week(s) (enter response as integer) .

Assume the network and data in the following Table A: ACTIVITY Immediate Predecessor (s) Time (weeks) A 3 3 B -- 4 C B 4 D A 4 E A, B 5 F D, E 6 G C, E 2. The duration for the project is weeks (enter response as integer)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!