Question: b. The duration for path B-C-G is _________ weeks (enter response as integer). c. The slack for activity C is ________ week(s) (enter response as

b. The duration for path B-C-G is _________ weeks (enter response as integer).
c. The slack for activity C is ________ week(s) (enter response as integer) .
Assume the network and data in the following Table A: ACTIVITY Immediate Predecessor (s) Time (weeks) A 3 3 B -- 4 C B 4 D A 4 E A, B 5 F D, E 6 G C, E 2. The duration for the project is weeks (enter response as integer)Step by Step Solution