Question: Attached is a CPM network with activity times in weeks - a . Determine the critical path. b . How many weeks will the project

Attached is a CPM network with activity times in weeks - a. Determine the critical path.
b. How many weeks will the project take to complete?
c. Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?
Attached is a CPM network with activity times in