Question: Problem 5 - 1 4 ( Static ) Here is a CPM network with activity times in weeks: a . Determine the critical path. A
Problem Static
Here is a CPM network with activity times in weeks:
a Determine the critical path.
AEGCD
ABCD
AEFD
b How many weeks will the project take to complete?
Number of weeks
c Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?
Number of weeks reduced