Question: b ) BDA 4 0 7 0 3 A direct time study was conducted at an assembly line which has a 1 2 - hour
b
BDA
A direct time study was conducted at an assembly line which has a hour operation per day. The operation is divided into five work elements: A B C D and as shown in Table Q Elements and were done on fully automatic machines, while other elements are manually done. Operators A and B were rated lower than normal, while Operator D was higher than normal. The company allocates a total allowance. Analyse the data and propose an appropriate standard time minunit for the overall assembly process.
marks
Table Q Direct time study data
tableJob Element,tableAverage Process TimeminutesABDE