Question: b . Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time ( weeks ) On critical path? Slack

b. Calculate the slack for each activity. Which activities are on the critical path?
Activity
Activity
Time(weeks)
On critical path?
Slack
(weeks)
A
2
Yes
No
enter your response here
B
8
No
Yes
enter your response here
C
5
No
Yes
enter your response here
D
12
Yes
No
enter your response here
E
11
Yes
No
enter your response here
F
5
No
Yes
enter your response here
G
4
Yes
No
enter your response here
H
9
No
Yes
enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!