Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 5 B 10

A project for improving a billing process has the following precedence relationships and activity times:

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

5

B

10

C

7

A

D

14

B, C

E

9

B

F

4

D

G

4

E

H

9

F, G

Part 2

a. Choose the correct network diagram below.

A.

SFA5B10C7E9D14F4G4H9

x y graph

B.

SFA5B10C7D14G4F4E9H9

x y graph

C.

SFA5B10C7D14G4F4E9H9

x y graph

D.

SFA5B10D14E9C7F4H9G4

x y graph

Part 3

b. Calculate the slack for each activity. Which activities are on the critical path?

Activity

Activity

Time (weeks)

On critical path?

Slack

(weeks)

A

5

No

Yes

enter your response here

B

10

No

Yes

enter your response here

C

7

No

Yes

enter your response here

D

14

Yes

No

enter your response here

E

9

Yes

No

enter your response here

F

4

Yes

No

enter your response here

G

4

No

Yes

enter your response here

H

9

No

Yes

enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!