Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 5 B 10
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 5 | |
| B | 10 | |
| C | 7 | A |
| D | 14 | B, C |
| E | 9 | B |
| F | 4 | D |
| G | 4 | E |
| H | 9 | F, G |
Part 2
a. Choose the correct network diagram below.
A.
SFA5B10C7E9D14F4G4H9
x y graph
B.
SFA5B10C7D14G4F4E9H9
x y graph
C.
SFA5B10C7D14G4F4E9H9
x y graph
D.
SFA5B10D14E9C7F4H9G4
x y graph
Part 3
b. Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On critical path? | Slack (weeks) |
| A | 5 | No Yes | enter your response here |
| B | 10 | No Yes | enter your response here |
| C | 7 | No Yes | enter your response here |
| D | 14 | Yes No | enter your response here |
| E | 9 | Yes No | enter your response here |
| F | 4 | Yes No | enter your response here |
| G | 4 | No Yes | enter your response here |
| H | 9 | No Yes | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts