Question: B . Consider the given below table and answer the questions: ( 4 Marks ) Write all possible paths for these tasks. ( 2 Marks

B. Consider the given below table and answer the questions: (4 Marks)
Write all possible paths for these tasks. (2 Marks)
Draw the PERT/CPM chart with all the details, following the convention of
CPM Chart. (3 Marks)
Write critical path by TaskID and how may days needed to complete the
project._(2 Marks)
C. Summarize one type of Testing and explain how you will be used in your project in details with
an examples? (3 Marks)