Question: b. How many weeks will it take to complete the project? c. How much slack does activity B have? Problem 5-7 (Algo) The following activities

b. How many weeks will it take to complete the project? c. How much slack does activity B have?
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B A A C B, D D E F TIME (WEEKS) 3 9 5 2 7 4 a. What is the critical path? A-B-E-G OA-C-D-F-G A-B-D-F-G A-C-D-E-GStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts