Question: b Suppose a project is being considered. The most probable time for completion for the first activity is 68 hours while the most optimistic time

b
b Suppose a project is being considered. The most
Suppose a project is being considered. The most probable time for completion for the first activity is 68 hours while the most optimistic time for completion is 46 hours and the most pessimistic time for completion is 81 hours. What is the expected number of hours for completion for the first activity? Round to two decimal places