Question: b) what is the minimum cost schedule? With the minimum cost-schedule, the project duration is ___ days c) What is the critical path for the
b) what is the minimum cost schedule? With the minimum cost-schedule, the project duration is ___ days
c) What is the critical path for the minimum-cost schedule?
The critical path for the minimum-cost schedule is____.
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 16. Activity Normal Cost ($) Normal Time (days) 5 Crash Time (days) 3 Immediate Predecessor(s) A B 4 3 4 3 Crash Cost ($) 1,600 1,200 900 1,500 1,700 1,400 1,200 500 3 800 1,000 600 1,200 1,500 1,300 900 500 2 A, B B C, D E 4 2 F 2 1 G 5 3 E H 5 5 G a. What is the project's duration if only normal times are used? The project duration is day(s). (Enter your response as an integer.)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts