Question: b) what is the probability that activity F alone will take between 44 and 46 days? B The following project has three independent paths as

b) what is the probability that activity F alone will take between 44 and 46 days?
b) what is the probability that activity F alone
B The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Most Optimistic Pessimistic Expected Variance Likely Activity Time Time Time of Time (days) (days) (days) Activity (days) 1 16 28 Start End 10 B 20 28 42 18 30 42 HD D 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed