Question: b, What is the probability that activity F alone will take between 44 and 46 days? The following project has three independent paths as shown

b, What is the probability that activity F alone will take between 44 and 46 days?b, What is the probability that activity F alone

The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Most A Activity Optimistic Time (days) Likely Time (days) Pessimistic Expected Variance Time Time of (days) (days) Activity 11-2 D Start End A 10 16 28 B 20 28 42 -10 1-3 E F 18 30 42 D 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed