Question: Babbit Manufacturing is using a Kanban system for a component part. The daily demand for the component is 800 brackets. Workday is 8 hr. A
Babbit Manufacturing is using a Kanban system for a component part. The daily demand for the component is 800 brackets. Workday is 8 hr. A container with 30 parts can be manufactured and delivered in 72min. The safety factor is set to 5% of hourly demand. What is hourly demand? 800 100 50 72