Question: BAC = 200 PV = 100 AC = 120 EV = 80 Assuming that all future work will be performed at the budgeted rate, the
BAC=200PV=100AC=120EV=80 Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC) is: 180. 120. 200. 140