Question: QUESTION 4 BAC = 200 PV = 100 AC = 120 EV = 80 Assuming that all future work will be performed at the budgeted

QUESTION 4 BAC = 200 PV = 100 AC = 120 EV = 80

QUESTION 4 BAC = 200 PV = 100 AC = 120 EV = 80 Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC) is: 120. 200 140. 180