Question: Barring a change in the project scope and given a Schedule Performance Index ( SPI ) that is 0 . 8 9 , the most

Barring a change in the project scope and given a Schedule Performance Index (SPI) that is 0.89, the most reasonable inference to draw is that
a) The project will likely finish later than planned.
b) The project will likely cost more than planned.
c) The project will likely cost less than planned.
d) The project will likely be on-time and on-budget.
e) The project will likely finish earlier than planned.