Question: Based on Table B, Consider that the maximum resource hours available per week are 15, determine which weeks are overcommitted. Question 1 Consider the following

Based on Table B, Consider that the maximum

Based on Table B, Consider that the maximum

Based on Table B, Consider that the maximum resource hours available per week are 15, determine which weeks are overcommitted.

Question 1 Consider the following project information: Table A. Activity Predecessor Total Float Duration in Weeks Resource Hours Needed/Week Total Resources Required A 3 6 18 B 5 A 2 4 20 7 A 4 28 D 3 3 B, C 6 18 E 5 B 4 2 10 F 4 D 4 16 2 5 3 6 H 5 E, F, G 6 30 Total 146 Table B. Activity Duration ES EF LS LF Float A 3 0 5 0 5 B 5 5 12 5 12 7 12 21 12 21 D 3 12 17 16 21 E 5 21 28 21 28 F 4 17 23 22 28 G 2 21 25 24 28 H 5 28 35 28 35 Question 1 Consider the following project information: Table A. Activity Predecessor Total Float Duration in Weeks Resource Hours Needed/Week Total Resources Required A 3 6 18 B 5 A 2 4 20 7 A 4 28 D 3 3 B, C 6 18 E 5 B 4 2 10 F 4 D 4 16 2 5 3 6 H 5 E, F, G 6 30 Total 146 Table B. Activity Duration ES EF LS LF Float A 3 0 5 0 5 B 5 5 12 5 12 7 12 21 12 21 D 3 12 17 16 21 E 5 21 28 21 28 F 4 17 23 22 28 G 2 21 25 24 28 H 5 28 35 28 35

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!