Question: Based on the baseline schedule provided, what is the Early Start for Activity H? B FS-2 10 10 A FS+2 D E H 5 10

Based on the baseline schedule provided, what is

Based on the baseline schedule provided, what is the Early Start for Activity H? B FS-2 10 10 A FS+2 D E H 5 10 5 5 SS+5 F 10 10 a. 26 b. 23 c. 22 d. 29