Question: Based on the BOM shown below, A 2 weeks B (4) 4.4 weeks C(4) 4.4 weeks D (1) 4 weeks D (3) 4 weeks G

Based on the BOM shown below, A 2 weeks B (4) 4.4
Based on the BOM shown below, A 2 weeks B (4) 4.4 weeks C(4) 4.4 weeks D (1) 4 weeks D (3) 4 weeks G (2) 2 weeks F(1) 3 weeks E (5) 2 weeks F(5) 3 weeks F(5) E (5) 2 weeks 3 weeks S What is the cumulative lead time for end item A? (Round your answer to 1 decimal Cumulative lead time weeks