Question: Based on the BOM shown below, A 3 weeks B (2) 2.5 weeks C(1) 2.5 weeks D(1) 3 weeks D (2) 3 weeks G (1)

Based on the BOM shown below, A 3 weeks B (2) 2.5

Based on the BOM shown below, A 3 weeks B (2) 2.5 weeks C(1) 2.5 weeks D(1) 3 weeks D (2) 3 weeks G (1) 3 weeks F (1) 3 weeks F(3) E (3) 2 week E (3) 2 weeks F(3) 3 weeks 3 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks