Question: Based on the calculations from question 1, what is the planned time-phased value (PV) of Saldan Construction project at the end of week 7 ?

Based on the calculations from question 1, what is the planned time-phased value (PV) of Saldan Construction project at the end of week 7?


Based on the calculations from question 3, what is the Cumulative Actual Cost (AC) of Saldan Construction project at the end of week 7?
Below is the planned time-phased value (PV) of Saldan Construction project. Week BAC 1 2 3 4 5 6 7 00 9 9 10 Task 1 50 5 5 25 20 Task 2 90 5 10 15 15 15 10 10 8 2 Task 3 60 5 10 15 15 7 5 3 Total 200 Cumulative T. Ff A B 1 US x x Please, complete the two bottom rows Total and Cumulative Week BAC 1 2 13 4 15 6 6 7 18 19 10 Task 1 50 5 5 25 120 Task 2 90 5 10 15 15 15 10 10 18 2 ask 3 160 5 10 15 15 7 5 13 Total 200 humulative 80 This table is representing the actual cost (AC) of Saldan Construction project. Week 1 2 3 4. 5 6 7 Task 1 5 25 20 Task 2 5 15 20 15 15 10 Task 3 5 10 15 15 Total Cumulative Calculate the total and cumulative actual costs (AC) at the end of week 7? Show your calculations in the table belowStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts