Question: Based on the chart showing activities on the critical path, which activity(s) would you crash to save exactly four weeks? Baseline Crash Activity A B

Based on the chart showing activities on the
Based on the chart showing activities on the critical path, which activity(s) would you crash to save exactly four weeks? Baseline Crash Activity A B c D Time 10 2 14 6 Cost $4,000 $6,000 $22,000 $9,000 $14,000 $18,000 Time 8 2 12 5 7 Cost $6,000 $6,000 $26,000 $10,000 $19,000 $36,000 E 9 F 00 4