Question: Based on the following PERT analysis. For all high-level activities in this project, calculate the following: 1. Optimistic time (5 marks) 2. Most likely time

Based on the following PERT analysis.

Description: 6 5 days 6 days 2 days 5 2 4 days 5 days 2 days 8 1 7 2 days 6 days 8 days 3 1 days Activity No. Earthwork Drainage installat

For all high-level activities in this project, calculate the following:

1. Optimistic time (5 marks)

2. Most likely time (5 marks)

3. Pessimistic time (5 marks)

4. Expected activity time (5 marks)

5. Standard deviation (5 marks)

6. Variance (5 marks)

7. For one date ahead of most likely completion date, calculate Z and hence the probability of completion by that date. (5 marks)

8. For one date behind the most likely completion date, calculate Z and hence the probability of completion by that date.
 



5 days 6 6 days 2 days 5 2 4 days 5 days 2 days 1 2 days 7 8 6 days 3 4 1 days 8 days No. Activity 1 Earthwork 2 Drainage installation 3 Foundations 4 Concrete slab 5 Precast walls installation 6 Roof steelwork erection 7 Plumbing and electrical work 8 Fit-out and finishing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!