Question: Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity Description Predecessors Time (days) 3 A B

Based on the following table, a) draw the network
Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity Description Predecessors Time (days) 3 A B initial market evaluations R&D scale up obtaining legal permits launch to market A A,B C 2 4 3 D E C D 2