Question: Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity A Predecessors Time (days) 2. B .

Based on the following table, a) draw the network
Based on the following table, a) draw the network for supposed processes b) calculate the project duration Activity A Predecessors Time (days) 2. B . B Nw 3 2 Description initial market evaluations R&D Supply of production materials and equipment scale up obtaining legal permits launch to market 2 D E D | U F D, E 4