Question: draw the network for supposed processes b) calculate the project duration Activity Description Predecessors Time (days) A initial market evaluations - 3 B R&D A

draw the network for supposed processes b) calculate the project duration
Activity
Description
Predecessors
Time (days)
A
initial market evaluations
-
3
B
R&D
A
2
C
scale up
A, B
4
D
obtaining legal permits
C
3
E
launch to market
C, D
2