Question: Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, LS, LF c) Calculate the project duration Activity Predecessors

Based on the following table, a) Draw the network for supposed processes b) Calculate ES, EF, LS, LF c) Calculate the project duration Activity Predecessors Time (days) 2 B Description initial market evaluations R&D Supply of production materials and equipment C A,B Nw D E scale up 2 D 5 obtaining legal permits launch to market F D, E 4