Question: Q4. Based on the given table below, answer the questions. (25 points) Show all calculation steps in the answers and fill the table also otherwise

Q4. Based on the given table below, answer the questions. (25 points)

Show all calculation steps in the answers and fill the table also otherwise downvote will be given.

Direct Costs

Activiy

Slope

Max.

Normal

Crash

ID

Crash Time

Time

Cost ($)

Time

Cost ($)

A

6

110

3

170

B

7

160

3

280

C

13

120

10

210

D

15

120

11

240

E

6

200

4

230

F

11

80

7

180

G

8

120

5

240

CPM is A C E F G

a) Calculate the Max. crash time and slope (10 points)

b) Crash the project for 8 weeks, calculate the total cost before and after crashing (15 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!