Question: Q4. Based on the given table below, answer the questions. (25 points) Show all calculation steps in the answers and fill the table also otherwise
Q4. Based on the given table below, answer the questions. (25 points)
Show all calculation steps in the answers and fill the table also otherwise downvote will be given.
|
|
|
| Direct Costs | |||
| Activiy | Slope | Max. | Normal | Crash | ||
| ID |
| Crash Time | Time | Cost ($) | Time | Cost ($) |
| A |
|
| 6 | 110 | 3 | 170 |
| B |
|
| 7 | 160 | 3 | 280 |
| C |
|
| 13 | 120 | 10 | 210 |
| D |
|
| 15 | 120 | 11 | 240 |
| E |
|
| 6 | 200 | 4 | 230 |
| F |
|
| 11 | 80 | 7 | 180 |
| G |
|
| 8 | 120 | 5 | 240 |
CPM is A C E F G
a) Calculate the Max. crash time and slope (10 points)
b) Crash the project for 8 weeks, calculate the total cost before and after crashing (15 points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
