Question: Based on the given table below, answer the questions. (25 points) Show all calculation steps in the answers CPM is A C E F G
Based on the given table below, answer the questions. (25 points)
Show all calculation steps in the answers
CPM is A C E F G
|
|
|
| Direct Costs | |||
| Activiy | Slope | Max. | Normal | Crash | ||
| ID |
| Crash Time | Time | Cost ($) | Time | Cost ($) |
| A |
|
| 6 | 110 | 3 | 170 |
| B |
|
| 7 | 160 | 3 | 280 |
| C |
|
| 13 | 120 | 10 | 210 |
| D |
|
| 15 | 120 | 11 | 240 |
| E |
|
| 6 | 200 | 4 | 230 |
| F |
|
| 11 | 80 | 7 | 180 |
| G |
|
| 8 | 120 | 5 | 240 |
a) Calculate the Max. crash time and slope (10 points)
b) Crash the project for 8 weeks, calculate the total cost before and after crashing (15 points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts