Question: Based on the information below: a. Develop a CPM tabular report b. Draw a schedule Gantt Chart, including the activity float. c. What is the
Based on the information below:
- a. Develop a CPM tabular report
- b. Draw a schedule Gantt Chart, including the activity float.
- c. What is the minimum time to complete this project?
- d. What is the project end date?
- e. What is the critical path (if any)?
- f. If you only had one resource to your disposal, which days would have a resource overload (if any)? Discuss in detail the implications thereof as well as you approach
- regarding implementation.
- g. The client has informed you that the project duration is 18 working days, discuss in detail the implications thereof as well as you approach regarding implementation.
- h. The client has informed you that the project duration is 14 working days, discuss in detail the implications thereof as well as you approach regarding implementation.
The project starts on Monday 16 November 2020. Work days are five (5) days a week from Monday to Friday. Saturdays and Sundays are non-working days. Public holidays are working days.
Detail of the activities are given below:
| Predecessors | Activity Number | Duration (work days) |
| - | A | 4 |
| A, C | B | 2 |
| B | C | 3 |
| C, F | D | 2 |
| A | E | 3 |
| E | F | 1 |
| D | G | 5 |
Some of these activities cannot be started until others have been completed:
- A is a start activity
- B and E must follow A
- C must follow B
- F must follow E
- D must follow C and F
- G must follow D