Question: Based on the network diagram below, calculate the earliest start and earliest finish, latest start and latest finish for Activity D, and select the correct

Based on the network diagram below, calculate the
Based on the network diagram below, calculate the earliest start and earliest finish, latest start and latest finish for Activity D, and select the correct answer. C2 E,2 H2 4,7 B.11 F,5 1,4 D.10 G,4 Earliest start = 7 earliest finish = 17, latest start -10, latest finish - 20 Earliest start 7 earliest finish - 17 latest start 9, latest finish - 19 OC Earliest start - 7 earliest finish 17 latest start 7, latest finish - 17 Od Earliest start = 7, earliest finish=17, latest start = 11, latest finish - 21