Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 3 8

Given is a CPM project network diagram as shown below. Given is a CPM project network diagram as shown

Activity

Start

A

B

C

D

E

F

G

H

End

day

0

3

8

2

5

5

7

2

4

0

a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)