Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 3 8
Given is a CPM project network diagram as shown below. 
| Activity | Start | A | B | C | D | E | F | G | H | End |
| day | 0 | 3 | 8 | 2 | 5 | 5 | 7 | 2 | 4 | 0 |
a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)