Question: Based on the table below, how many days will it take to complete the project? Activity Duration IPA A 2 none B 3 A C
-
Based on the table below, how many days will it take to complete the project?
Activity Duration IPA A 2 none B 3 A C 2 A D 5 B, C E 3 C F 2 D, E A 10
B 11
C 12
D 17
Step by Step Solution