Question: Based on the table below, how many days will it take to complete the project? Activity Duration IPA A 2 none B 3 A C

  1. Based on the table below, how many days will it take to complete the project?

    Activity Duration IPA
    A 2 none
    B 3 A
    C 2 A
    D 5 B, C
    E 3 C
    F 2 D, E
    A

    10

    B

    11

    C

    12

    D

    17