Question: Based on the table given below, answer the questions. Show all calculation steps in the answers Maximum Crash Time Direct Costs Activity Slope Normal Crash
Based on the table given below, answer the questions.
Show all calculation steps in the answers
| Maximum Crash Time | Direct Costs | |||||
| Activity | Slope | Normal | Crash | |||
| ID | Time | Cost (USD) | Time | Cost (USD) | ||
| S |
|
| 17 | 4750 | 15 | 5650 |
| T |
|
| 13 | 2660 | 12 | 3000 |
| U |
|
| 25 | 8200 | 21 | 11200 |
| V |
|
| 14 | 4175 | 11 | 6500 |
| W |
|
| 19 | 7300 | 17 | 9700 |
| X |
|
| 16 | 6400 | 15 | 8200 |
| Y |
|
| 9 | 3800 | 7 | 5000 |
CPM is T U W Y
a) Calculate the Maximum Crash Time and Slope.
b) Crash the project by 5 weeks.
c) What is the total cost of the project before and after crashing? Briefly explain all the costs included in the calculation.