Question: 4. Based on the table given below, answer the questions. (20 points) Show all calculation steps in the answers Direct Costs Activity Slopel Max Normal

4. Based on the table given below, answer the

4. Based on the table given below, answer the questions. (20 points) Show all calculation steps in the answers Direct Costs Activity Slopel Max Normal Crash ID Crash Time Time Cost ($) Time Cost ($) A 4 100 2 160 B 5 160 2 280 11 9 120 100 210 190 D 13 10 E 7 200 3 F 9 80 6 300 170 250 G 6 150 4 CPM is ABEG a) Calculate the Max Crash Time and slope (10 points) b) Crash the project for 6 weeks, calculate the total cost after project crash (10 points)