Question: Because it is the _ _ _ _ _ _ succession of activities, the critical path determines the _ _ _ _ _ _ _

Because it is the ______ succession of activities, the critical path determines the _______ possible completion date of the project.
a. shortest, earliest
b. longest, latest
c. longest, earliest
d. shortest, latest