Question: Because it is the _ _ _ _ _ _ succession of activities, the critical path determines the _ _ _ _ _ _ _
Because it is the succession of activities, the critical path determines the possible completion date of the project.
a shortest, earliest
b longest, latest
c longest, earliest
d shortest, latest