Question: Which statement regarding critical path and non-critical path is WRONG? A. Critical path is the path with the highest number of activities. B. Only non-critical
Which statement regarding critical path and non-critical path is WRONG?
A. Critical path is the path with the highest number of activities. B. Only non-critical path activity can have positive slack time. C. Critical path determines the completion time of the project. D. None of the above.