Question: Below are items needing to be evaluated using a critical path network TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A B D E 3

Below are items needing to be evaluated using a

Below are items needing to be evaluated using a critical path network TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A B D E 3 2 2. 3 5 3 3 A 4 1 1 1 2 3 3 1 2 4 4 B C,D DE F, G 11 5 6 5 4 4 What is the critical path? It is What is the expected project completion time. It will take days. Round up to FULL days i.e. 15.9 goes to 16 and 16.1 goes to 17. Word Bank: 15 14.67 days 15 days B-E-G-H 14.67 BEGH