Question: Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days.

Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 4 3 196 396
B A 5 3 279 586
C A 1 1 217 185
D B and C 5 4 502 553
E D 3 2 505 903

-What is the total time of this project? Please give your answer in days

-What are the total normal cost of this project? Please give your answer in $.

-If you crash this project to reduce the total time by one day (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.

-If you crash this project to reduce the total time by three days (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.

Thank you for your help with this question, it is appreciated! :)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!